Pilgangoora – Pilbara Minerals

Wastewater Icon

PROJECT AT A GLANCE

PROJECT TYPE:
Lithium Mine & Processing Plant
Owner:

Pilbara Minerals

Engineer:

Minnovo

Contractor:

RCR

Pipe Material:

Carbon Steel, Schedule 10 Stainless Steel, Rubber Lined

Pipe Size:

1/2 - 32"

Location:

Port Hedland, Western Australia

Solutions:

  • Compressed Construction Schedule
  • Ease & Speed of Installation

Pilbara Minerals’ 100%-owned Pilgangoora Lithium-Tantalum Project, located near Port Hedland in Western Australia’s resource-rich Pilbara region, is one of the biggest new lithium ore deposits in the world.

With an aggressive deadline to start operations as soon as possible, Victaulic® products were chosen to provide the fastest pipe joining method across a range of services and pipe materials from 1/2” to 32” (15mm – 800mm). For the small bore stainless steel chemical and compressed air lines, Victaulic Vic-Press™ provided a fast and simple joining solution that enabled the site to use off-the-shelf Schedule 10 stainless. Likewise, on the standard weight carbon steel systems, Victaulic grooved couplings made installation a breeze. With QuickVic™ Installation-Ready™ couplings, the process water and compressed air lines were joined up to 10 times faster than alternative methods. Victaulic was able to provide solutions for the full range of sizes up to 32” (800mm) OD, including those for rubber-lined carbon steel pipe.

Ultimately, a post-construction analysis calculated a two to three-month savings on construction time and a savings of roughly $1 million in labor costs.

AT A GLANCE

PROJECT TYPE:
Lithium Mine & Processing Plant
Wastewater Icon
Owner:

Pilbara Minerals

Engineer:

Minnovo

Pipe Material:

Carbon Steel, Schedule 10 Stainless Steel, Rubber Lined

Location:

Port Hedland, Western Australia

Contractor:

RCR

Pipe Size:

1/2 - 32"

Solutions:

  • Compressed Construction Schedule
  • Ease & Speed of Installation

Pilbara Minerals’ 100%-owned Pilgangoora Lithium-Tantalum Project, located near Port Hedland in Western Australia’s resource-rich Pilbara region, is one of the biggest new lithium ore deposits in the world.

With an aggressive deadline to start operations as soon as possible, Victaulic® products were chosen to provide the fastest pipe joining method across a range of services and pipe materials from 1/2” to 32” (15mm – 800mm). For the small bore stainless steel chemical and compressed air lines, Victaulic Vic-Press™ provided a fast and simple joining solution that enabled the site to use off-the-shelf Schedule 10 stainless. Likewise, on the standard weight carbon steel systems, Victaulic grooved couplings made installation a breeze. With QuickVic™ Installation-Ready™ couplings, the process water and compressed air lines were joined up to 10 times faster than alternative methods. Victaulic was able to provide solutions for the full range of sizes up to 32” (800mm) OD, including those for rubber-lined carbon steel pipe.

Ultimately, a post-construction analysis calculated a two to three-month savings on construction time and a savings of roughly $1 million in labor costs.